| Event Date | Bid Status | Details |
|
12/03/2010 | In Review |
2 Bids received, opened publically, and read aloud.
Purchasing commenced and completed responsiveness and compliance review of the 2 bids received. Both were found responsive and compliant.
|
|
12/06/2010 | In Review |
The bid of the apparent lowest responsive and responsible bidder was forwarded to the Department of Natural Resources for their review.
|
|
12/07/2010 | In Review |
Arlington Power Equipment, Inc. will be recommended for award by the General Superintendant.
|
|
12/10/2010 | Awarded |
The General Superintendant approved the contract award to Arlington Power Equipment, Inc.
|
|
12/13/2010 | Awarded |
Contract execution process initiated by Purchasing.
|
|
12/17/2010 | Contracted |
Contract fully executed.
|